Calculate a direct-material price variance

Measure whether the actual price paid for material differs from its standard price, using the actual quantity purchased or used required by the question.

Section 4.2 · Standard costing

Cambridge International AS & A Level Accounting 9706 · Topic 4.2 · 2026–2028 · 4.2

Cambridge International AS & A Level Accounting 9706, 2026–2028 syllabus, Version 2. Topic 4.2 teaches standard costing, the listed material, labour, fixed-overhead and sales variances, their causes and relationships, and evidence-based business decisions. Practice is self-checked, not an official Cambridge grade. Full timed Papers 1–4 and human subject-teacher review remain outstanding.

Before you begin

  • Use Topic 2.1–2.2 cost behaviour, contribution and absorption-costing ideas. In each question, identify the period, actual output, budget and standard before calculating a variance.

Work on paper. Try each question before revealing help, and explain why your method works.

Quick readiness check

A price variance measures the difference between…

What you will learn

  • Apply the direct-material price-variance formula
  • Keep price and quantity units consistent
  • Interpret the result without assuming its cause

Compare the same actual quantity at two prices

Material price variance = (standard price − actual price) × actual quantity, using a convention where a positive cost saving is labelled favourable. Equivalently, compare standard cost of that actual quantity with the actual amount paid. State whether the question uses quantity purchased or quantity used; follow the supplied data and convention.

If the actual price is higher, actual cost exceeds the standard cost for that same quantity and the price variance is adverse. If the actual price is lower, it is favourable on price alone.

Material price variance = (SP − AP) × AQ

Explain, then investigate

Price can change because of supplier terms, bulk discounts, market prices, delivery charges, exchange rates or a change in material specification. The calculation does not identify which explanation applies.

If price is calculated on quantity purchased while usage is based on quantity consumed, the variances may cover different timing or quantities. Read the question carefully and avoid combining results that do not share a basis.

Pause and explain

SP is $5.20/kg, AP is $5.00/kg and AQ is 900 kg. What is the price direction?

Put the idea to work

Worked example

Standard price is $8 per kg. A business buys 1,250 kg at $8.40 per kg. Calculate the price variance.

Show the worked solution
  1. Standard cost of the actual quantity = 1,250 × $8 = $10,000.
  2. Actual cost = 1,250 × $8.40 = $10,500.
  3. Actual cost is $500 higher, so the price variance is adverse.

Answer $500 adverse. Equivalently, (8.00 − 8.40) × 1,250 = −$500, interpreted as adverse.

Try a topic test

Choose Easy, Normal or Difficult. Save your answers and open worked review after finishing.

Test this topic →

From guided practice to a new situation

Write your answer and reasoning first. Use a hint only if you are stuck. The model solution is for self-checking; your written work is not automatically marked.

1 · Guided

SP is $6/kg; actual quantity is 2,400 kg; AP is $6.25/kg. Calculate the price variance.

Give me a hint

Compare both prices for the same 2,400 kg.

Compare my reasoning
  1. Standard cost = 2,400 × 6 = $14,400.
  2. Actual cost = 2,400 × 6.25 = $15,000.
  3. Actual cost is $600 above standard.

$600 adverse.

Look for these in your work

  • Use actual quantity 2,400 kg
  • Compare costs $14,400 and $15,000
  • Label the $600 overspend adverse
2 · Independent

SP is $3.50 per metre, AP is $3.36, and actual quantity is 1,800 metres. Calculate the variance.

Give me a hint

A lower actual price is favourable for a cost when quantity is held constant.

Compare my reasoning
  1. Price saving per metre = 3.50 − 3.36 = $0.14.
  2. Multiply by 1,800 metres: 0.14 × 1,800 = $252.
  3. The actual purchase cost is below standard for this quantity.

$252 favourable.

Look for these in your work

  • Price difference is $0.14
  • Multiply by actual metres
  • Interpret as favourable cost direction
3 · Transfer

A supplier cuts the price by 8% but adds a delivery fee and switches to thinner packaging. Which records should be checked before explaining the price variance?

Give me a hint

Separate invoice price, landed cost, specification and quantity/quality outcomes.

Compare my reasoning
  1. Check the invoice price and delivery charge included in actual material cost.
  2. Confirm whether the material specification changed and whether the standard still matches it.
  3. Review returns, defects and usage to see whether a lower purchase price affected consumption or quality.

Check the landed purchase cost, the standard specification, actual quantity and quality evidence. The price variance alone cannot show whether the apparent saving improved total performance.

Look for these in your work

  • Landed cost checked
  • Standard specification checked
  • Usage and quality linked

Common mistakes

  • Using the standard quantity allowed instead of the actual quantity
  • Multiplying price difference by output units without converting to material quantity
  • Treating a favourable purchase price as proof of lower total cost
Recall without your notes

What can you explain now?

Which quantity is multiplied by the material price difference?

Compare with the explanation

The relevant actual material quantity

The variance compares standard and actual price for an actual quantity.

After trying it yourself, choose your next review. This is your self-assessment.

Your review choice appears on Today. Sign in to sync it across devices.

Make it stick

State the material price variance formula and the actual quantity it uses.

If you needed the solution, close it and solve the problem again from a blank page. A correct answer is stronger when you can explain the reason for each step.

Keep learning Accounting

Course scope and assessment

197 original lessons teach Topics 1.1–1.6 and 2.1–2.2, plus Topics 3.1–3.5 and 4.1–4.4, with explained, staged practice mapped to the listed syllabus objectives, including all four Topic 1.5 objectives. Topic 3.1 covers partnership changes, clubs and societies, manufacturing accounts and the limited-company statement set. Topic 3.2 covers all nine named IAS at Cambridge's stated main-provisions level, ethical principles, audit and stewardship. Topic 3.3 covers business mergers and acquisitions, goodwill, consideration, ledger entries, post-acquisition statements and evaluation. Topic 3.4 covers controlled accounting-data conversion and integrity checks. Topic 3.5 covers all nine appendix ratios, exact prescribed formulae, interrelationships, limitations and justified stakeholder recommendations. Topic 4.1 covers cost pools, cost drivers, ABC overhead allocation, unit costs, selling prices, comparisons, uses, limitations and business decisions. Topic 4.2 covers standard costing, all listed cost and sales variances, their causes and relationships, budget improvement and non-financial decision factors. Topic 4.3 covers linked master-budget schedules, all nine listed budgets, limiting factors, flexible-budget statements and reconciliations, target behaviour and supported decisions. Topic 4.4 covers future project cash flows, payback, ARR, NPV, IRR, method limits and balanced recommendations; Cambridge excludes discounted payback and residual-value questions. All 17 topics have full mapped sequences. The separately published 2029 syllabus is not covered. Practice is self-checked and does not award Cambridge grades. Full timed Papers 1–4 and human subject-teacher review remain outstanding.

StudyForA · Learn with understanding

Original teaching content and links to official sources. Check your exam year and qualification before using a resource.