Create schedules from dependencies

Use durations, prerequisites and shared resources to find a feasible earliest finishing time.

Cambridge AS & A Level Thinking Skills 9694 · Problem solving / 26-2.1 / 26-2.3 / 28-2.5

Original StudyForA scenarios and formative model answers; no Cambridge marks, predicted grades or certified mastery. Alternative reasoned answers may be valid. Full-length unseen papers, a wider mixed-problem bank and calibrated specialist teacher marking remain outstanding.

Before you begin

  • Read tables and instructions in English
  • Use arithmetic, ratios and whole-number constraints

Work on paper. Try each question before revealing help, and explain why your method works.

Quick readiness check

Before calculating, what should you identify?

What you will learn

  • Schedule dependent and parallel tasks
  • Explain a lower bound on completion time

Separate duration from dependency

Write each task’s duration and what must finish before it starts. Parallel work is allowed only when the resources and stated rules permit it. Earliest start is the latest finish among the task’s prerequisites; earliest finish adds its duration.

Two workers: A takes 20 minutes; after A, B takes 30 and C takes 15 and can run in parallel. D takes 10 after both B and C. A runs 0–20, B 20–50, C 20–35 and D 50–60. Adding every duration gives 75, which ignores the permitted overlap.

Check shared resources and prove earliest

The A–B–D chain takes 60 minutes, so no compliant schedule can finish earlier. The schedule reaches that bound, proving earliest completion. If B and C need the same machine, their overlap is impossible even with two workers, and they must be scheduled serially.

For real clock times convert consistently, including journeys across midnight. State whether setup, rest and travel count in the duration; do not assume omitted time is zero when the question supplies it elsewhere.

Sources for this lesson

Pause and explain

When can D start if it needs B and C finished?

Put the idea to work

Worked example

Find earliest completion of A, B, C and D with the stated parallel resources.

Show the worked solution
  1. Finish A at minute 20.
  2. Run B and C in parallel; B finishes last at 50.
  3. D then finishes at 60, matching the A–B–D lower bound.

Answer Earliest completion is 60 minutes. The long dependency chain requires sixty, and the proposed schedule meets every prerequisite without a resource conflict.

Try a topic test

Choose Easy, Normal or Difficult. Save your answers and open worked review after finishing.

Test this topic →

From guided practice to a new situation

Write your answer and reasoning first. Use a hint only if you are stuck. The model solution is for self-checking; your written work is not automatically marked.

1 · Guided

Guided: If B and C share one machine, find completion time.

Give me a hint

They must run one after another.

Compare my reasoning
  1. A finishes at 20.
  2. B and C take another 45 serial minutes.
  3. D adds ten minutes.

Completion takes 75 minutes. B and C cannot overlap on one machine, so A, both middle tasks and D form a serial workload of 20+30+15+10.

Look for these in your work

  • Recognises the conflict
  • Serialises correctly
  • Includes D
2 · Independent

Independent: Tasks P (12 minutes) and Q (18 minutes) start together on separate machines. R (7 minutes) starts after both. Find the earliest finish.

Give me a hint

R waits for the slower prerequisite.

Compare my reasoning
  1. P ends at 12 and Q at 18.
  2. R starts at 18.
  3. Add seven minutes.

Earliest finish is minute 25. Q–R requires 18+7=25 minutes, and running P alongside Q attains that lower bound.

Look for these in your work

  • Allows permitted overlap
  • Uses the later finish
  • Justifies earliest
3 · Transfer

Application: A shuttle departs 23:50, travels 35 minutes, then needs a 10-minute walk. What is the venue arrival time, and can it meet a 00:30 deadline?

Give me a hint

Carry the date across midnight.

Compare my reasoning
  1. The shuttle arrives at 00:25 the next day.
  2. The walk ends at 00:35.
  3. Compare with 00:30 on that next day.

Venue arrival is 00:35 the next day, five minutes late. Ignoring the day change or the final walk would produce an invalid deadline check.

Look for these in your work

  • Crosses midnight
  • Includes walking
  • Checks the correct day

Common mistakes

  • Adding durations that can overlap
  • Overlapping tasks that share a resource
  • Calling a feasible schedule optimal without a lower bound
Recall without your notes

What can you explain now?

When can D start if it needs B and C finished?

Compare with the explanation

After the later of their finish times

Every prerequisite must be completed.

After trying it yourself, choose your next review. This is your self-assessment.

Your review choice appears on Today. Sign in to sync it across devices.

Make it stick

When can D start if it needs B and C finished?

If you needed the solution, close it and solve the problem again from a blank page. A correct answer is stronger when you can explain the reason for each step.

Keep learning Thinking Skills

Course scope and assessment

Thirty-four original lessons include 102 guided, independent and application tasks. All 15 earlier section entries and 39 revised skill entries link to teaching; a linked map is not proof of full exam readiness. Both AS and A Level study the whole content, with more demanding combined tasks at A Level. Original StudyForA scenarios and formative model answers; no Cambridge marks, predicted grades or certified mastery. Alternative reasoned answers may be valid. Full-length unseen papers, a wider mixed-problem bank and calibrated specialist teacher marking remain outstanding. June and November entries are available, including private candidates. Confirm the exam year, administrative-zone timetable and centre entry with your exams officer. AS uses Papers 1 and 2 in the same series; full A Level uses all four papers, either together or through an authorised staged route. Carry-forward rules and time limits must be checked for the relevant series.

StudyForA · Learn with understanding

Original teaching content and links to official sources. Check your exam year and qualification before using a resource.