Estimate IRR by interpolation

Estimate the zero-NPV rate between trial rates with opposite NPV signs.

Section 4.4 · Investment appraisal

Cambridge International AS & A Level Accounting 9706 · Topic 4.4 · 2026–2028 · 4.4
Exam scope and assessment notes

Cambridge International AS & A Level Accounting 9706, 2026–2028 syllabus, Version 2. This topic covers future net cash flows, payback, ARR, NPV, IRR and supported investment decisions. Discounted payback and questions involving a residual value at the end of a project are excluded by Cambridge. Practice is self-checked, not an official Cambridge grade. Full timed Papers 1–4 and human subject-teacher review remain outstanding.

Before you begin

  • Use AS Topics 1.5–1.6 for profit, depreciation and financial analysis, and Topic 2.1 for contribution. Keep accounting profit, project cash flow and the time value of money distinct.

Work on paper. Try each question before revealing help, and explain why your method works.

Quick readiness check

NPV is +$1,000 at 8% and −$1,000 at 12%. Estimate IRR.

What you will learn

  • Identify the lower and higher trial rates
  • Apply interpolation
  • Explain why the result is approximate

Interpolate between opposite signs

With NPV positive at lower rate L and negative at higher rate H, approximate IRR = L + [NPV at L ÷ (NPV at L − NPV at H)] × (H − L). Keeping the negative NPV signed is equivalent to adding its absolute value in the denominator.

This estimates where NPV crosses zero. It is approximate because the NPV curve is not exactly a straight line across a wide interval.

Check the rate and sign

The fraction should lie between 0 and 1 when trial NPVs have opposite signs; the estimate should lie between the rates.

Use the same currency and period assumptions at both trial rates. Two NPVs with the same sign do not bracket IRR.

Pause and explain

NPV is +$3,000 at 5% and −$1,000 at 9%. What fraction of the rate interval is added above 5%?

Put the idea to work

Worked example

NPV is +$2,400 at 10% and −$1,600 at 15%. Estimate IRR.

Show the worked solution
  1. Rate interval = 5 percentage points.
  2. Positive share = 2,400 ÷ (2,400 + 1,600) = 0.6.
  3. Estimate = 10% + 0.6 × 5% = 13%.

Answer Estimated IRR is approximately 13%.

Try a topic test

Choose Easy, Normal or Difficult. Save your answers and open worked review after finishing.

Test this topic →

From guided practice to a new situation

Write your answer and reasoning first. Use a hint only if you are stuck. The model solution is for self-checking; your written work is not automatically marked.

1 · Guided

NPV is +$1,800 at 11% and −$1,200 at 16%. Estimate IRR.

Give me a hint

Use positive NPV divided by the absolute sign-change total.

Compare my reasoning
  1. Fraction = 1,800 ÷ 3,000 = 0.6.
  2. Interval = 5 percentage points.
  3. Estimate = 11% + 0.6 × 5% = 14%.

Estimated IRR is approximately 14%.

Look for these in your work

  • Fraction correct
  • Interval correct
  • Rate within bracket
2 · Independent

NPV is +$5,000 at 9% and −$3,000 at 17%. Estimate IRR.

Give me a hint

Find the positive-NPV share of the sign change.

Compare my reasoning
  1. Fraction = 5,000 ÷ 8,000 = 0.625.
  2. Interval = 8 percentage points.
  3. Estimate = 9% + 0.625 × 8% = 14.0%.

Estimated IRR is 14.0%.

Look for these in your work

  • Signed values handled
  • Interval correct
  • Result rounded
3 · Transfer

An IRR estimate is 18.5%, but trial rates were 10% and 15%. What should you check?

Give me a hint

A valid interpolation remains between trial rates.

Compare my reasoning
  1. Recheck the NPV signs and rate order.
  2. Check the formula and opposite-sign requirement.
  3. Recalculate before using the estimate.

The result is outside the bracket, so recheck signs, rate order or arithmetic.

Look for these in your work

  • Range check used
  • Potential error located
  • Decision held

Common mistakes

  • Using a wrong sign in the interpolation ratio
  • Using only positive NPV as denominator
  • Reporting a rate outside the trial interval
Recall without your notes

What can you explain now?

For interpolation, what should the trial NPVs normally show?

Compare with the explanation

Opposite signs

Opposite signs place zero between the tested rates.

After trying it yourself, choose your next review. This is your self-assessment.

Your review choice appears on Today. Sign in to sync it across devices.

Make it stick

State interpolation in words and give one reason the result is approximate.

If you needed the solution, close it and solve the problem again from a blank page. A correct answer is stronger when you can explain the reason for each step.

Keep learning Accounting

Course scope and assessment

197 original lessons teach Topics 1.1–1.6 and 2.1–2.2, plus Topics 3.1–3.5 and 4.1–4.4, with explained, staged practice mapped to the listed syllabus objectives, including all four Topic 1.5 objectives. Topic 3.1 covers partnership changes, clubs and societies, manufacturing accounts and the limited-company statement set. Topic 3.2 covers all nine named IAS at Cambridge's stated main-provisions level, ethical principles, audit and stewardship. Topic 3.3 covers business mergers and acquisitions, goodwill, consideration, ledger entries, post-acquisition statements and evaluation. Topic 3.4 covers controlled accounting-data conversion and integrity checks. Topic 3.5 covers all nine appendix ratios, exact prescribed formulae, interrelationships, limitations and justified stakeholder recommendations. Topic 4.1 covers cost pools, cost drivers, ABC overhead allocation, unit costs, selling prices, comparisons, uses, limitations and business decisions. Topic 4.2 covers standard costing, all listed cost and sales variances, their causes and relationships, budget improvement and non-financial decision factors. Topic 4.3 covers linked master-budget schedules, all nine listed budgets, limiting factors, flexible-budget statements and reconciliations, target behaviour and supported decisions. Topic 4.4 covers future project cash flows, payback, ARR, NPV, IRR, method limits and balanced recommendations; Cambridge excludes discounted payback and residual-value questions. All 17 topics have full mapped sequences. The separately published 2029 syllabus is not covered. Practice is self-checked and does not award Cambridge grades. Full timed Papers 1–4 and human subject-teacher review remain outstanding.

StudyForA · Learn with understanding

Original teaching content and links to official sources. Check your exam year and qualification before using a resource.