Discount each future project cash flow, total present values and subtract the initial investment.

Cambridge International AS & A Level Accounting 9706 · Topic 4.4 · 2026–2028 · 4.4
Exam scope and assessment notes

Cambridge International AS & A Level Accounting 9706, 2026–2028 syllabus, Version 2. This topic covers future net cash flows, payback, ARR, NPV, IRR and supported investment decisions. Discounted payback and questions involving a residual value at the end of a project are excluded by Cambridge. Practice is self-checked, not an official Cambridge grade. Full timed Papers 1–4 and human subject-teacher review remain outstanding.

Before you begin

  • Use AS Topics 1.5–1.6 for profit, depreciation and financial analysis, and Topic 2.1 for contribution. Keep accounting profit, project cash flow and the time value of money distinct.

Work on paper. Try each question before revealing help, and explain why your method works.

Quick readiness check

Future cash-flow PV totals $72,000 and initial investment is $60,000. Find NPV.

What you will learn

  • Calculate present values by year
  • Find NPV from a cash-flow schedule
  • Apply the decision rule with its assumptions

Build an NPV schedule

NPV = total present value of future net cash inflows and outflows − initial investment. Discount each future flow with its matching period factor, then add the present values.

Positive NPV means discounted future net inflows exceed the initial investment at the chosen rate. Negative NPV means they fall short. Zero NPV just meets the return represented by that rate.

Check what the result depends on

Use the stated rate and horizon. The initial investment at time 0 is not discounted.

A positive NPV supports acceptance under the assumptions, but forecasts, capacity and non-financial factors still need review. Compare projects on a consistent basis.

Pause and explain

A project has NPV −$4,000 at the required rate. What does this mean?

Put the idea to work

Worked example

A project costs $80,000 now. Inflows are $35,000, $40,000 and $45,000; factors at 10% are 0.909, 0.826 and 0.751. Calculate NPV.

Show the worked solution
  1. PV year 1 = $31,815.
  2. PV years 2 and 3 = $33,040 and $33,795; total = $98,650.
  3. NPV = 98,650 − 80,000 = $18,650.

Answer NPV is $18,650 at 10%.

Try a topic test

Choose Easy, Normal or Difficult. Save your answers and open worked review after finishing.

Test this topic →

From guided practice to a new situation

Write your answer and reasoning first. Use a hint only if you are stuck. The model solution is for self-checking; your written work is not automatically marked.

1 · Guided

Initial investment is $50,000 and future PVs total $58,400. Calculate NPV.

Give me a hint

Subtract the time-0 outflow.

Compare my reasoning
  1. 58,400 − 50,000 = $8,400.
  2. The sign is positive.
  3. Label the rate basis from the question.

NPV is positive $8,400 at the supplied rate.

Look for these in your work

  • PV used
  • Cost deducted
  • Sign interpreted
2 · Independent

A project costs $120,000. Discounted inflows are $31,000, $38,000, $34,000 and $29,000. Calculate NPV.

Give me a hint

Add PVs before deducting the initial cost.

Compare my reasoning
  1. Total PV = $132,000.
  2. NPV = 132,000 − 120,000 = $12,000.
  3. The discounted forecast exceeds investment by $12,000.

NPV is positive $12,000 at the supplied rate.

Look for these in your work

  • PVs totalled
  • Initial investment deducted
  • Meaning stated
3 · Transfer

A project has positive NPV but relies on an untested sales forecast. What should the decision paper include?

Give me a hint

Keep the calculation, forecast risk and conditions visible.

Compare my reasoning
  1. Show NPV at the stated rate and key assumptions.
  2. Test plausible lower sales or higher costs.
  3. State what evidence should be met before commitment.

Report the result as conditional on its assumptions, test downside scenarios and set approval conditions.

Look for these in your work

  • NPV stated
  • Sensitivity tested
  • Conditions proposed

Common mistakes

  • Discounting the time-0 investment again
  • Applying the same factor to each year
  • Treating a positive NPV as certainty
Recall without your notes

What can you explain now?

NPV is…

Compare with the explanation

Total PV of future net cash flows − initial investment

NPV compares discounted future flows with the initial outflow.

After trying it yourself, choose your next review. This is your self-assessment.

Your review choice appears on Today. Sign in to sync it across devices.

Make it stick

What does a positive NPV mean at the selected rate?

If you needed the solution, close it and solve the problem again from a blank page. A correct answer is stronger when you can explain the reason for each step.

Keep learning Accounting

Course scope and assessment

197 original lessons teach Topics 1.1–1.6 and 2.1–2.2, plus Topics 3.1–3.5 and 4.1–4.4, with explained, staged practice mapped to the listed syllabus objectives, including all four Topic 1.5 objectives. Topic 3.1 covers partnership changes, clubs and societies, manufacturing accounts and the limited-company statement set. Topic 3.2 covers all nine named IAS at Cambridge's stated main-provisions level, ethical principles, audit and stewardship. Topic 3.3 covers business mergers and acquisitions, goodwill, consideration, ledger entries, post-acquisition statements and evaluation. Topic 3.4 covers controlled accounting-data conversion and integrity checks. Topic 3.5 covers all nine appendix ratios, exact prescribed formulae, interrelationships, limitations and justified stakeholder recommendations. Topic 4.1 covers cost pools, cost drivers, ABC overhead allocation, unit costs, selling prices, comparisons, uses, limitations and business decisions. Topic 4.2 covers standard costing, all listed cost and sales variances, their causes and relationships, budget improvement and non-financial decision factors. Topic 4.3 covers linked master-budget schedules, all nine listed budgets, limiting factors, flexible-budget statements and reconciliations, target behaviour and supported decisions. Topic 4.4 covers future project cash flows, payback, ARR, NPV, IRR, method limits and balanced recommendations; Cambridge excludes discounted payback and residual-value questions. All 17 topics have full mapped sequences. The separately published 2029 syllabus is not covered. Practice is self-checked and does not award Cambridge grades. Full timed Papers 1–4 and human subject-teacher review remain outstanding.

StudyForA · Learn with understanding

Original teaching content and links to official sources. Check your exam year and qualification before using a resource.