Prepare a labour budget
Convert budgeted output into labour hours and cost using the standard time and wage rate.
Cambridge International AS & A Level Accounting 9706, 2026–2028 syllabus, Version 2. Topic 4.3 covers budgetary control, linked master-budget schedules, spreadsheets, limiting factors, flexible budgets, reconciliations, behavioural effects and supported decisions. Practice is self-checked, not an official Cambridge grade. Full timed Papers 1–4 and human subject-teacher review remain outstanding.
Before you begin
- Use AS Topics 2.1–2.2 for cost behaviour, contribution and budgeting foundations. For each schedule, label the period, units, price, inventory policy, timing assumptions and opening balance before calculating.
Work on paper. Try each question before revealing help, and explain why your method works.
Quick readiness check
A worker is paid $20 for each hour. Is $20 a time quantity or a rate?
What you will learn
- Calculate labour hours for planned output
- Calculate labour cost by worker category
- Evaluate staffing and capacity assumptions
Build hours from the production plan
Labour hours budget = units to produce × standard labour hours per unit. Labour cost budget = budgeted hours × standard wage rate per hour. Use production units, not sales units, when inventory affects output.
If products use different skills or rates, calculate separate schedules for each worker category and add them only after applying the correct standard time and rate.
Labour budgets need realistic capacity
The plan can reveal staffing, overtime, training or subcontracting needs. Compare required hours with available hours by skill and period; total annual hours may conceal a short-term bottleneck.
A budgeted average wage can hide overtime premiums or a changed skill mix. Include appropriate pay assumptions and non-financial factors such as safety, fatigue, employee availability and service quality.
Pause and explain
Make 900 units at 2.5 hours each and $12/hour. What is labour cost?
Worked example
Production is budgeted at 2,400 units. Each unit needs 0.75 hours and labour costs $16 per hour. Calculate hours and labour cost.
Show the worked solution
- Hours = 2,400 × 0.75 = 1,800.
- Cost = 1,800 × $16.
- Budgeted labour cost = $28,800.
Answer Budget 1,800 labour hours costing $28,800.
Try a topic test
Choose Easy, Normal or Difficult. Save your answers and open worked review after finishing.
Test this topic →From guided practice to a new situation
Write your answer and reasoning first. Use a hint only if you are stuck. The model solution is for self-checking; your written work is not automatically marked.
A factory plans 1,600 units, 1.25 hours each at $18/hour. Find hours and cost.
Give me a hint
Calculate hours, then multiply by the hourly rate.
Compare my reasoning
- Hours = 1,600 × 1.25 = 2,000.
- Cost = 2,000 × $18.
- Cost = $36,000.
2,000 hours costing $36,000.
Look for these in your work
- Hours correct
- Rate applied
- Total cost correct
Product A: 1,200 units at 0.5 hours and $16/hour. Product B: 800 units at 1.5 hours and $20/hour. Calculate total labour cost.
Give me a hint
Cost each product separately because hours and rates differ.
Compare my reasoning
- A hours = 1,200 × 0.5 = 600; A cost = 600 × $16 = $9,600.
- B hours = 800 × 1.5 = 1,200; B cost = 1,200 × $20 = $24,000.
- Total labour cost = $33,600.
Total labour cost is $33,600 for 1,800 hours.
Look for these in your work
- A cost correct
- B cost correct
- Costs totalled
A budget meets total labour hours but requires 600 skilled hours in one week when only 400 are available. What should managers revise?
Give me a hint
Check the weekly skill constraint, not only the period total.
Compare my reasoning
- Identify a 200-hour shortfall for the required skill in that week.
- Assess approved overtime, rescheduling, training or subcontracting options and their costs.
- Revise the schedule only after checking deadlines, quality, safety and worker availability.
The plan has a 200-hour skilled-labour shortfall. Management should test feasible timing or staffing options and include their cost and service effects.
Look for these in your work
- Shortfall quantified
- Options and costs considered
- Operational conditions included
Common mistakes
- Using units sold instead of units produced
- Multiplying units by wage rate without hours per unit
- Ignoring different labour grades or overtime
What can you explain now?
What is the first step in calculating a labour budget?
Compare with the explanation
Production units × standard hours per unit
Planned output determines standard hours before those hours are costed.
After trying it yourself, choose your next review. This is your self-assessment.
Your review choice appears on Today. Sign in to sync it across devices.
Make it stick
Give the formulas for labour hours and labour cost in a production budget.
If you needed the solution, close it and solve the problem again from a blank page. A correct answer is stronger when you can explain the reason for each step.